Double Eagle Pipeline Moving Eagle Ford Condensate to Corpus Christi

Double Eagle Pipeline - Eagle Ford Condensate System
Double Eagle Pipeline - Eagle Ford Condensate System

Double Eagle Pipeline, LLC, a joint venture between Kinder Morgan and Magellan Midstream, has started moving condensate to Corpus Christi.

The pipeline is part of a project that was started by Copano and Magellan, but is operated by Kinder Morgan who purchased Copano earlier in 2013.

Condensate is moving from a truck unloading facility in Three Rivers to Magellan's Corpus Christi Terminal. From the Corpus Terminal, condensate can reach local petrochemical plants, as well as water borne export options.

This leg is just a portion of what is a $150 million project that includes 140 miles of 12-inch pipelines. The system connects with other Kinder Morgan pipelines in the area as well.

The next leg of the pipeline from Gardendale (near Cotulla) to Three Rivers is expected to be online in the third quarter of 2013. Initial capacity is planned at 100,000 b/d, but the system can be expanded to handle 150,000 b/d.

The pipeline was supported by long-term commitments from Talisman and Statoil.