Copano Energy Eagle Ford Shale Update – May 2012

Copano Energy has Announced Almost $1 Billion in Eagle Ford Projects
Copano Energy Eagle Ford Midstream Map

Copano Eagle Ford Map | Click to Enlarge

Copano Energy provided an update on its Eagle Ford operations in May. Highlights include:

  • Copano is investing $1 billion in organic projects
  • Has committed volumes of ~1 Bcf/d with 10 year terms from producers
  • Houston Central (200 mmcfd)cryogenic plant is performing better than expected
  • Lean oil plant at Houston Central realizing lower recoveries than expected
  • New 400 mmcfd cryogenic plant at Houston Central will improve margins further Q1 2013. Another 400 mmcfd expansion coming in 2014
  • High NGL content in the Eagle Ford creates short-term constraints, but long-term opportunity

Other growth projects and notes

  • DK Pipeline extension will reach into McMullen County by Q2 2013 ($120 million)
  • Double Eagle Condensate Pipeline JV – Copano will spend $100 million on the 140 mile condensate gathering system. Building system in partnership with Magellan Midstream (100,000 b/d of capacity planned)

Find the full presentation at copanoenergy.com

The following two tabs change content below.
R.T. Dukes

R.T. Dukes

Managing Editor at EagleFordShale.com
R.T. is the managing editor of EagleFordShale.com. In prior roles, he advised major oil companies on strategy, the macro business environment, and opportunity screening. 2503 Robinhood, Houston, TX, 77005, U.S.A. | Telephone: 832.429.4790